Integration of Early Contractor Involvement (ECI) Within Nigeria's Traditional Design-Bid-Build (DBB) Public Procurement System
DOI:
10.29303/alexandria.v7i2.1863Published:
2026-09-30Downloads
Abstract
This study examines the integration of Early Contractor Involvement (ECI) within Nigeria's traditional Design-Bid-Build (DBB) public procurement system. It responds to persistent performance challenges in Nigeria's public construction sector, particularly cost overruns, delays, adversarial relationships, poor buildability, and limited innovation, by examining how ECI can be integrated within the existing Public Procurement Act (PPA) 2007 framework. Adopting a qualitative case study design, the study drew data from 30 senior stakeholders, including public-sector clients, contractors, consultants, and legal and academic experts in the Federal Capital Territory (FCT), Abuja. The findings indicate that the fragmented and sequential nature of DBB contributes to cost escalation, prolonged delays, claims-oriented relationships, poor buildability, and restricted innovation. The major drivers of ECI integration include improved cost and schedule certainty, collaborative risk management, enhanced buildability, and value engineering, while key barriers include the legal emphasis on open competitive bidding, lowest responsive bid selection, and existing institutional constraints. On the basis of these findings, the study proposes a PPA-compliant two-stage framework for integrating ECI within Nigeria's existing public procurement regime. The study concludes that the strategic application of ECI principles within the current legal framework can provide a practical pathway for improving value for money, strengthening collaboration, reducing transactional inefficiencies, and promoting more effective project delivery in Nigeria's public construction sector.
Keywords:
Early Contractor Involvement (ECI) Design-Bid-Build (DBB) Public Procurement Risk Management Buildability Value EngineeringReferences
Abimbola, J. (2015). Presidential Abandoned Projects Audit Commission report. Nigerian Federal Government.
Adekunle, W. (2020, June). The role of construction sector in the quest for inclusive growth in Nigeria [Technical Report]. The Nigerian Economic Summit Group.
Atkinson, R. J., Tennakoon, M., and Wedawatta, G. (2022). Use of new models of construction procurement to enhance collaboration in construction projects: the UK construction industry perspective. Journal of Financial Management of Property and Construction, 28(1), 45–63.
Babalola, O. D., Ugah, U. K., and Ndimako, O. O. (2024). Evaluating governmental constraints on construction in Nigeria: A review [Preprint]. Preprints.org.
Braun, V., and Clarke, V. (2006). Using thematic analysis in psychology. Qualitative Research in Psychology, 3(2), 77–101.
Construction Front Team. (2025). What is an ECI contract? (And how it works). Construction Front.
Construction Industry Institute. (2021). Potential for construction industry improvement: Volume II – Assessment results, conclusions and recommendations (SD‑62). Construction Industry Institute.
Fei, W., Opoku, A., Agyekum, K., Oppon, J. A., Ahmed, V., Chen, C., and Lok, K. L. (2021). The critical role of the construction industry in achieving the sustainable development goals (SDGs): Delivering projects for the common good. Sustainability, 13(16), 9112.
GlobalData. (2023, May 3). Global construction industry growth will remain sluggish in 2023, forecasts GlobalData. GlobalData.
Gransberg, D. D. (2016). Comparing construction manager–general contractor and federal early contractor involvement project delivery methods. Transportation Research Record, 2573(1), 18–25.
Gransberg, N. J., and Gransberg, D. D. (2020). Public project construction manager-at-risk contracts: Lessons learned from a comparison of commercial and infrastructure projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 12(1), 04519039.
International Labour Organization. (2022). World Employment and Social Outlook: Trends 2022. International Labour Organization.
Ishtiaque, T. A., Klakegg, O. J. (2025). Effects of early contractor involvement in small construction projects: lessons from Norway. Built Environment Project and Asset Management.
Ishtiaque, T. A., Wondimu, P. A., and Klakegg, O. J. (2025). Likelihood of early contractor involvement (ECI) benefits in infrastructure versus building projects: the client’s perception. International Journal of Construction Management, 25(10), 1227–1238.
Ishtiaque, T. A., Wondimu, P. A., Memic, N., Andersen, B. S., Lædre, O., and Klakegg, O. J. (2025). Ranking the benefits of early contractor involvement: a client’s perspective. International Journal of Construction Management, 25(6), 728–739.
Kinnunen, J., Saunila, M., Ukko, J., and Rantanen, H. (2022). Strategic sustainability in the construction industry: Impacts on sustainability performance and brand. Journal of Cleaner Production, 368, 133063.
Kumaraswamy, M. M. (2024). Collaborative contracting and relationship-based teamworking. In Routledge Handbook of Construction Project Procurement and Delivery (pp. 184–199). Routledge.
Laryea, S., and Watermeyer, R. (2016). Early contractor involvement in framework contracts. Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 169(1), 4–16.
Mekawy Mohammed, M. R. (2020). A framework for using BIM in mass-customization and prefabrication in the AEC industry (Doctoral dissertation, Technische Universität München).
Meng, X., and Humphreys, P. (2015). The application of early contractor involvement and its impact on project performance. International Journal of Project Organisation and Management, 7(4), 339–351.
Moon, H., Kim, K., Lee, H. S., Park, M., Williams, T. P., Son, B., and Chun, J. Y. (2020). Cost performance comparison of design-build and design-bid-build for building and civil projects using mediation analysis. Journal of Construction Engineering and Management, 146(9), 04020113.
New Zealand Government Procurement. (2019, October). Early contractor involvement: Information sheet (Construction Procurement Guidelines). New Zealand Government.
Obieje, I. D. (2019). Improving the achievement of value for money in construction procurement under the Nigerian Public Procurement ACT (2007). University of Salford (United Kingdom).
Odusami, K. T., and Olusanya, O. (2020). Clients’ contribution to delays on building projects in Lagos Metropolis. The Quantity Surveyor, October–December, Vol. 26.
Omoniyi, E. O., Akinola, V. O., and Alake, O. (2021). Impact of characteristics of design-bid-build delivery system on construction project performance in Nigeria. LAUTECH Journal of Civil and Environmental Studies, 6(1), 170–183.
Osuizugbo, I. C., Omer, M. M., Rahman, R. A., and Oshodi, O. S. (2024). A systematic search and review of early contractor involvement in construction project development. Built Environment Project and Asset Management, 14(6), 835–857.
Park, J., and Kwak, Y. H. (2017). Design-bid-build (DBB) vs. design-build (DB) in the US public transportation projects: The choice and consequences. International Journal of Project Management, 35(3), 280–295.
Rahman, S. H. A., Endut, I. R., Faisol, N., and Paydar, S. (2014). The importance of collaboration in construction industry from contractors’ perspectives. Procedia-Social and Behavioral Sciences, 129, 414–421.
Rahmani, F. (2021). Challenges and opportunities in adopting early contractor involvement (ECI): Client’s perception. Architectural Engineering and Design Management, 17(1-2), 67–76.
Rahmani, F., Khalfan, M., and Maqsood, T. (2022). A conceptual model for selecting early contractor involvement (ECI) for a project. Buildings, 12(6), 786.
Saidu, I., and Shakantu, W. (2017). An investigation into cost overruns for ongoing building projects in Abuja, Nigeria. Acta Structilia, 24(1), 53–72.
Salla, D. E. (2020). Comparing performance quality of design-bid-build (DBB) and design-build (DB) project delivery methods in Nigeria. African Journal of Earth and Environmental Science, 2(2).
Shrestha, P. P., and Fernane, J. D. (2017). Performance of design-build and design-bid-build projects for public universities. Journal of Construction Engineering and Management, 143(3), 04016101.
Shwarka, S. M., & Anigbogu, N. A. (2012, September). Impact of the Public Procurement Reform on public building projects delivery in Nigeria. In Proceedings 28th Annual ARCOM Conference (pp. 969-977).
Wondimu, P. A., Klakegg, O. J., and Lædre, O. (2020). Early contractor involvement (ECI): ways to do it in public projects. Journal of Public Procurement, 20(1), 62–87.
License
Copyright (c) 2026 Omoh Paul Igbebo, Ajakor Uche, Eze Gideon Chigozie

This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors who publish with ALEXANDRIA (Journal of Economics, Business, Tourism, and Entrepreneurship), agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution 4.0 International License. This license allows authors to use all articles, data sets, graphics and appendices in data mining applications, search engines, web sites, blogs, and other platforms by providing an appropriate reference. The journal allows the author(s) to hold the copyright without restrictions and will retain publishing rights without restrictions.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in ALEXANDRIA (Journal of Economics, Tourism, Hospitality, and Entrepreneurship).
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).